Look at the sample project plan for the development of an internet site. Notice that all the tasks have different deadlines. You are part of the team developing the internet site. Answer the following questions.
| 15 Feb |
20 Mar |
10 May |
1 Sep |
15 Dec |
1 Feb |
30 Jun |
|
| Business proposal | |||||||
| Analyse site contents | |||||||
| Create the internet site | |||||||
| Test the internet site | |||||||
| Management sign off | * | ||||||
| Install the internet site | |||||||
| Train staff to use the internet site | |||||||
| Hand over the management | * | ||||||
Check your Answers
Back to Activities