Activity 3

Look at the sample project plan for the development of an internet site. Notice that all the tasks have different deadlines. You are part of the team developing the internet site. Answer the following questions.

  15
Feb
20
Mar
10
May
1
Sep
15
Dec
1
Feb
30
Jun
Business proposal arrow            
Analyse site contents   arrow          
Create the internet site     arrow        
Test the internet site       arrow*    
Management sign off           *  
Install the internet site         arrow  
Train staff to use the internet site           arrow
Hand over the management             *
  1. What is the deadline for testing the internet site?
  2. What is the start date and end date for training staff in the use of the internet site?
  3. What is the scheduled date for the internet site to be handed over to management?
  4. What do you think is meant by “management sign off”?

Check your Answers